PPG Thailand (Leschaco Thailand Ltd.) & USA (TransProject LLC) have successfully delivered two large ABB Transformers from the ABB factory in Thailand up to DDP Gillette, Wyoming, USA. The two transformers were shipped separately due to delivery scheduling and the attached photos were taken by TransProject in Casper, Wyoming during lifting of the transformers from railcar to truck. Each transformer was accompanies by approximately 115cbm of accessories in wooden boxes which were packed by Leschaco’s packing station at the ABB facility.
|
|
|
 |
Transformer No. 1
Dim: 6650 x 3720 x 3740 (mm)
Weight: 98 MT
POL: Laem Chabang, Thailand
Carrier: Nordana
POD: Houston, USA
Routing: Houston – Casper, WY by Railcar
Casper – Gillette by Road
Transit time: June – August 2009
|
|
|
 |
Transformer No. 2 (Winter photos - 18 degrees Celsius):
Dim: 6890 x 3800 x 3830 (mm)
Weight: 73 MT
POL: Laem Chabang, Thailand
Carrier: Rickmers
POD: Long Beach, USA
Routing: Long Beach – Casper, WY by Railcar
Casper – Gillette by Road
Transit Time: September – December 2009
|
 |